Switchboard Replacement

  • switch panel maintenance

Switchboard Replacement

Working in conjunction with the facilities team, Jarrards completed the supply and installation of 3 new 2000 amp LV switchboards over a Christmas shutdown.  The new switchboards were designed by Jarrards in close co ordination with their manufacturer to suit the existing installation following a full discrimination survey.  Auto changeover, standby generator and temporary mobile generator supply inputs where incorporated into the sections.  The boards were designed with terminations to match the existing cable positions which enabled the switchboards to be replaced without any cable modification.  New 400mm single core cabling was installed from each of the clients transformers on new ladder containment to Power Optimisation Units.

Project Details

Location
Sutton, London

Duration
2 weeks

Client
Global Publisher

Value
£280k